Cutover of cable though Roadworks.

Reason for change
Northpower Fibre is planning an outage to transfer an existing backbone cable to a newly installed cable through the State Highway 1 road works in Whangarei.
Due to roadwork’s, the existing backbone cable will be transferred to a new cable through the job.

Activities – expected timeline (NZST)

Outage window 1 Date 4/07/19-5/7/19
Outage window Time 23.45-03.30
Approximate Outage Duration per circuit 15 minutes

July 4, 2019 23:45 NZST
Active – Scheduled maintenance is starting.