Southern Cross Planned Maintenance

July 25, 2019 00:01 NZST
Scheduled – Work Reference SR#236827_7
Southern Cross Planned Maintenance Software Update UTC 25th July 2019

There is an ongoing fault on the node that need to be fixed by a software update on our Ciena platform by Southern Cross equipment vendor tomorrow.

A 2-hour Maintenance Window has been established to enable a number of nodes (SR#236827_6) to be updated as well in the same Maintenance Window.

Impact:
The nodes will be out of service for a period of up to 25 minutes, and as 4 nodes are being updated, and depending on the routing of individual circuits, there could be up to 4 outages during the Maintenance Window.

This activity is programmed in the following Maintenance Window:
UTC 1700 hrs to 1900 hrs on Thursday, 25th July 2019

July 26, 2019 05:00 NZST
Active – Scheduled maintenance is starting.

July 26, 2019 07:00 NZST
Completed – Scheduled maintenance is complete.

Comments are closed.